Efficient Road Design

Progress impacted by COVID-19. Budget constraints created by the economic impact of the pandemic may result in further objective delays or discontinuing work. Departments will complete this analysis for the December 2020 update.
By June 2021, Public Works will reduce construction changes orders to 10% or less of the bid amount for all construction projects.

Key Steps

1 2 3 4
Establish procedures for constructability reviews at 30%, 60% and final stages of plans, specifications and estimates (PS&E). Assign a Civil Engineer in the construction management division to be the primary reviewer to relay comments back to engineering. Establish yearly "lessons learned" at the conclusion of the construction season with Construction, Engineering and Maintenance staff.  
Plan Reference: Collaborating Depts:
Target:
Baseline: Progress:
3.A.i, 3.C.ii, 6.D.ii PLN 10% of Project Costs 33% -30% (40%)